Assignment 3: Defining the Project Scope
Review the project case. Determine the scope of the District 4 Production Warehouse Move project from the information provided in the case. Using the Project Scope Checklist, prepare a scope document for review and approval by the project sponsor prior to starting the project.
Project Scope Checklist
1. Project objective
2. Deliverables
3. Milestones
4. Technical requirements
5. Limits and exclusions
6. Reviews with customer
Argosy MGT402 Module 2 Assignment 2
Assignment 2: Project Team and Stakeholder Management – Essay
Read the project case for this assignment.
As the project manager for the District 4 Warehouse Move project, you will need to determine who your stakeholders and project team members are for this project. Remember that anyone connected to the project who has an interest or stake in the project should be considered as a stakeholder. This would include the project team, vendors and management among possible others.
After you have determined who your stakeholders are, determine who will need to be a part of the project team. Develop a 2-3 page paper (650-750 words) in the form of a Microsoft Word document, not including the header and reference pages, defining the following:
1. How will project communications and interactions work between the project manager, the stakeholders and the project team?
2. What are some of the issues you, as the project manager will need to be concerned about in forming the project team?
3. What, if any, situational factors exist that may affect the project team’s performance?
4. What are some project pitfalls you will want to watch out for as you execute this project?
Argosy MGT402 Module 3 Assignment 2
Assignment 2: LASA – Project Planning – Developing the Project Plan and Determining Critical Path
Using the District4WarehouseMove WBS.xls provided, create a project plan for the District 4 Warehouse Move project. Use the PDF document, Project Plan Check – District4Move, to check your work to be sure you have created your starting project plan correctly. ProjectLibre is required for this task. If you have not yet downloaded ProjectLibre, please click here and follow the directions to do so now.
Note: you will need to insert a column to include your WBS codes, then you will need to sequence the tasks to show tasks by work package.
Based upon the details in the WBS and the project case, determine which tasks need to be completed first and which tasks are dependent upon other tasks to be completed prior to starting. Using this information identify predecessors in your project plan’s predecessor column. Complete the predecessor column by entering the line number of tasks that must be completed in order for each task to start. This will create your project timeline.
Using ProjectLibre’s Network or flow diagram view, determine the critical path for this project. In a MS Word document, list the activities that are on the critical path. Considering the risks identified in the risk table below, identify which risks would be most likely to increase your project timeline. Justify your responses.
Submit both your completed project plan and your MS Word document.
District 4 Production Warehouse Move Project – Risk Table
1
Permits are not received per the schedule
2
Finish work contractors walk off the job half way through
3
Framing and drywall contractors are running behind schedule and can only produce half their crew as scheduled
4
Work benches are poor quality and 1/3 will have to be rebuilt
Argosy MGT402 Module 4 Assignment 2
Assignment 2: Project Schedule Changes
You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.
You originally were told the permits would only take 2 weeks to obtain but the contractors are telling you it will now take 3 weeks. You need to build the additional week into your schedule for each permit that will be obtained.
In addition, your framing and drywall contractors have just told you they are running late on their other jobs and can only release half their crew for your project. This will double their schedule.
Build the extra time into your schedule by doubling the installation work timelines for both the framing and drywall. Your project plan should also be updated with the new 3-week timeline for obtaining permits. Use the project plan you created for this task.
You are now looking at an extended project delivery date. Your project sponsor was very clear that you must be done in a 4 month timeframe so you will need to look at options for reducing your schedule to fit into the 4 month window.
You have an option of hiring another contractor to help with the framing and drywall work but it will increase your budget by $200,000.
Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation. Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan.
Submit both your updated project plan in PDF format and your PowerPoint presentation.
Argosy MGT402 Module 5 Assignment 1
Assignment 1: LASA – Final Project Report
Prepare an 8-10–page report in Word. This report should include a project history of your recent Trillo Apparel Company District 4 Production Warehouse Move experience over the last five weeks.
Your final report should include the following sections:
Executive Summary
Project Performance and Status Report
Organizational Structure
Project and Administrative Teams
Project Risk and Change Management
Project Management Techniques Employed
Conclusion
Include appropriate reports from your final project plans to corroborate your overall report. You may also use diagrams, charts, and other visual aids to make your report more effective. Assume that the report will be presented to the Board of Directors of Trillo Apparel Company. Your report should be done in the APA style.
In addition to the report, prepare an 7-9–slide presentation in PowerPoint that summarizes key aspects from the report.
Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteEdu. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.
Do you need help with this question?
Get assignment help from WriteEdu.com Paper Writing Website and forget about your problems.
WriteEdu provides custom & cheap essay writing 100% original, plagiarism free essays, assignments & dissertations.
With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.
Chat with us today! We are always waiting to answer all your questions.