You are a project manager on a project that uses earned value management. The project has the following budget and status: Project Duration (months)

You are a project manager on a project that uses earned value management. The project has the following budget and status:

Project Duration (months):

14

Current Reporting Period (month):

6

BAC:

$387,000

Cumulative PV:

$68,345

Cumulative AC:

$78,379

% of the project completed through the reporting period:

19%

Estimate to Complete:

$294,677

Based on this information, determine the following:

  1. Cumulative EV
  2. Schedule Variance (SV)
  3. Schedule Performance Index (SPI)
  4. Cost Variance (CV)
  5. Cost Performance Index (CPI)
  6. EAC (bottom-up)
  7. VAC (bottom-up)
  8. TCPI

Based on your calculations in Question 1 above, respond to the following:

  1. What is the status of project accomplishment performance through the current reporting period? Why?
  2. What is the status of project cost performance through the current reporting period? Why?
  3. Is the project projected to complete over- or underbudget? Why?
  4. Interpret the TCPI metric.

Based on your calculations in Question 1 above, an inexperienced and arrogant project analyst from the project management office has computed an additional metric: Cost Schedule Index, which equals SPI * CPI. He wants you to report this metric to the customer, instead of SPI and CPI separately. What should you do and why?

The Program Manager doubts your numbers. In particular, he does not believe your EAC number and requests that you calculate the EAC NOT assuming future performance will behave like past performance.

  1. Compute EAC when cost performance is negative and schedule dates must be met: EAC = AC + [(BAC – EV) / (CPI × SPI)]
  2. Compute EAC using actual costs to date and assuming ETC uses budgeted rate: EAC = AC + (BAC – EV)
  3. Interpret the results of the EAC in a.
  4. Interpret the results of the EAC in b.

Based on items a-d above, what do you think the Program Manager will request from you regarding the bottom-up EAC?

You are having a hallway conversation with the same project analyst from Question 3 who is realizing that he may not know as much about earned value management as he thought when he joined the company. Still, he is convinced that the following statements below are correct. How would you respond to him based on each statement (i.e., formulate a specific response and supporting rationale for each statement below)?

  1. EAC becomes Cumulative AC at project completion.
  2. Cumulative EV can be greater than BAC at project completion.
  3. EAC can be smaller than BAC at project completion.
  4. ETC can be greater than 0 at project completion.

    Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteEdu. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

    Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

    Do you need an answer to this or any other questions?

    Do you need help with this question?

    Get assignment help from WriteEdu.com Paper Writing Website and forget about your problems.

    WriteEdu provides custom & cheap essay writing 100% original, plagiarism free essays, assignments & dissertations.

    With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.

    Chat with us today! We are always waiting to answer all your questions.

    Click here to Place your Order Now