Throughout the past few weeks, you have learned about the type of leader you’d like to be and how you can use your leadership skills in project management. This week’s reading discussed Kotter’s eight-step model of planned organization, appreciative inquiry, and the psychological and emotional processes involved in successful change. Leading an IT project will require you to use all of these skills when working with stakeholders. One of the most important project tasks is to present the scoping information to the stakeholders.

For this assignment, you will revise your team’s project plan to present to stakeholders. Access your team’s draft of the Project Plan Template from the Wk 3 Team – Apply: Project Scope, Budget, and Timeline Stakeholder Meeting Role Play assignment, and re-save it so you can work on it individually.

Using information from the previous weeks’ assignments and instructor feedback, revise the Project Plan Template. Your new project plan should include the following revisions and additions:

  • A       summary of the project in Section 1: Summary
  • An       individual revision of the timeline from the Wk 3 Team – Apply:       Project Scope, Budget, and Timeline Stakeholder Meeting Role Play       assignment in Section 3: Schedule – Milestones
  • A       list of stakeholders (refer to the Wk 3 – Apply: Project Management       Flowchart and Summary assignment document) in Section 4: Resources
  • An       analysis of impact of change that should occur based on the risk       assessment in Section 6: Change Management
  • An       explanation and justification for the changes made in your revision of       your group’s decisions in an Appendix section

Cite two sources other than Intuit, Inc. company documents.

Format your citations according to APA guidelines.

Simple Cost Benefit Analysis Or

SIMPLE COST BENEFIT ANALYSIS TEMPLATE
COMPANY NAME Oracle DATE CONDUCTED 12/3/20
PROPOSED PRODUCT/INITIATIVE/SERVICE Exadata Cloud Service COMPLETED BY Kevin Moore
QUANTITATIVE ANALYSIS YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 TOTAL
NON-RECURRING COSTS
Hardware $ – 0 $ 100,000.00 $ – 0 $ 100,000.00 $ – 0 $ 200,000.00
Servers $ – 0 $ – 0 $ – 0 $ – 0 $ – 0 $ – 0
Desktop $ – 0 $ – 0 $ 100,000.00 $ – 0 $ – 0 $ 100,000.00
Telecommunication Equipment $ – 0 $ 20,000.00 $ – 0 $ 20,000.00 $ – 0 $ 40,000.00
Software (Packaged or Custom) $ 6,200.00 $ – 0 $ – 0 $ 6,200.00 $ – 0 $ 12,400.00
Computer Room Upgrades $ 5,000.00 $ – 0 $ 5,000.00 $ – 0 $ 5,000.00 $ 15,000.00
Furniture and Fixtures $ – 0 $ – 0 $ 15,000.00 $ – 0 $ 15,000.00 $ 30,000.00
Project Organizational/Support Costs $ 15,000.00 $ 7,000.00 $ 4,000.00 $ 3,000.00 $ 3,000.00 $ 32,000.00
Planning (upon Approval) $ 10,000.00 $ – 0 $ – 0 $ – 0 $ – 0 $ 10,000.00
Procurement $ – 0 $ – 0 $ – 0 $ – 0 $ – 0 $ – 0
Contract Negotiations $ 300.00 $ – 0 $ – 0 $ – 0 $ – 0 $ 300.00
Labor $ 160,000.00 $ 140,000.00 $ 120,000.00 $ 100,000.00 $ 80,000.00 $ 600,000.00
Infrastructure $ – 0 $ – 0 $ – 0 $ – 0 $ – 0 $ – 0
Development $ – 0 $ – 0 $ – 0 $ – 0 $ – 0 $ – 0
Business Process Owners (Users) $ 4,000.00 $ – 0 $ – 0 $ – 0 $ 4,000.00
Management $ 8,000.00 $ – 0 $ – 0 $ – 0 $ 8,000.00
Training of Employees (Pre-Implementation) $ – 0 $ – 0 $ – 0 $ – 0 $ – 0
Transition Costs (Parallel Systems) $ – 0 $ – 0 $ – 0 $ – 0 $ – 0
Post-Implementation Reviews $ 3,000.00 $ – 0 $ – 0 $ – 0 $ 3,000.00
TOTAL NON-RECURRING COSTS $ 211,500.00 $ 267,000.00 $ 244,000.00 $ 229,200.00 $ 103,000.00 $ 1,054,700.00
RECURRING COSTS
Hardware/Software $ – 0 $ – 0 $ – 0 $ – 0 $ – 0 $ – 0
Software Maintenance and Upgrades $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 50,000.00
Computer Supplies $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 100,000.00
Desktops (Incremental to the Project) $ – 0 $ – 0 $ – 0 $ – 0 $ – 0 $ – 0
Help Desk Support $ – 0 $ – 0 $ – 0 $ – 0 $ – 0 $ – 0
Ongoing Additional Labor $ – 0 $ – 0 $ – 0 $ – 0 $ – 0 $ – 0
IT Staff Costs (including Benefits) $ 500,000.00 $ 500,000.00 $ 500,000.00 $ 500,000.00 $ 500,000.00 $ 2,500,000.00
User Training $ 39,975.00 $ 39,975.00 $ 39,975.00 $ 119,925.00
Storage for Cloud $ 10,032.00 $ 10,032.00 $ 10,032.00 $ 10,032.00 $ 10,032.00 $ 50,160.00
Infrastructure $ 297,288.00 $ 297,288.00 $ 297,288.00 $ 297,288.00 $ 297,288.00 $ 1,486,440.00
Telecommunications $ 10,032.00 $ 10,032.00 $ 10,032.00 $ 10,032.00 $ 10,032.00 $ 50,160.00
Office Leases $ – 0 $ – 0 $ – 0 $ – 0 $ – 0 $ – 0
TOTAL RECURRING COSTS $ 887,327.00 $ 847,352.00 $ 887,327.00 $ 847,352.00 $ 887,327.00 $ 4,356,685.00
TOTAL COSTS $ 1,098,827.00 $ 1,114,352.00 $ 1,131,327.00 $ 1,076,552.00 $ 990,327.00 $ 5,411,385.00
QUANTITATIVE BENEFITS YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 TOTAL
REVENUES
Sell of old infastructure $ 40,000.00 $ – 0 $ – 0 $ – 0 $ – 0 $ 40,000.00
Sell of old hardware $ 15,000.00 $ 15,000.00
Sell of desktops $ 80,000.00 $ 80,000.00
TOTAL REVENUES $ 55,000.00 $ – 0 $ 80,000.00 $ – 0 $ – 0 $ 135,000.00
COST SAVINGS
Decreased Cost of Services Provided $ 1,650,000.00 $ 2,640,000.00 $ 2,970,000.00 $ 2,970,000.00 $ 3,300,000.00 $ 13,530,000.00
Savings from Business Process Improvements $ 660,000.00 $ 1,320,000.00 $ 1,980,000.00 $ 2,640,000.00 $ 3,300,000.00 $ 9,900,000.00
Productivity Gains $ 130,000,000.00 $ 260,000,000.00 $ 390,000,000.00 $ 520,000,000.00 $ 650,000,000.00 $ 1,950,000,000.00
Savings from Structural Changes $ 15,000.00 $ 20,000.00 $ 20,000.00 $ 55,000.00
Savings from Optimized Information (or Flow) $ 1,650,000.00 $ 2,640,000.00 $ 2,640,000.00 $ 2,970,000.00 $ 3,300,000.00 $ 13,200,000.00
Decreased Information Publishing Cost $ 100,000.00 $ 200,000.00 $ 300,000.00 $ 400,000.00 $ 500,000.00 $ 1,500,000.00
Reduced Staffing Cost (including Overtime) $ 50,000.00 $ 250,000.00 $ 300,000.00 $ 400,000.00 $ 500,000.00 $ 1,500,000.00
Reduced Staff Turnover Costs $ 40,000.00 $ 100,000.00 $ 150,000.00 $ 200,000.00 $ 250,000.00 $ 740,000.00
Rent $ 60,000.00 $ 120,000.00 $ 240,000.00 $ 360,000.00 $ 480,000.00 $ 1,260,000.00
TOTAL COST SAVINGS $ 134,225,000.00 $ 267,290,000.00 $ 398,580,000.00 $ 529,960,000.00 $ 661,630,000.00 $ 1,991,685,000.00
COST AVOIDANCE
Hardware $ 100,000.00 $ 100,000.00 $ 100,000.00 $ 300,000.00
Security $ 6,000.00 $ 6,000.00 $ 6,000.00 $ 6,000.00 $ 6,000.00 $ 30,000.00
Utilities $ 48,000.00 $ 96,000.00 $ 192,000.00 $ 288,000.00 $ 384,000.00 $ 1,008,000.00
TOTAL COST AVOIDANCE $ 154,000.00 $ 102,000.00 $ 298,000.00 $ 294,000.00 $ 490,000.00 $ 1,338,000.00
OTHER BENEFITS
(Enter Other Benefits Here) $ – 0
$ – 0
TOTAL OTHER BENEFITS $ – 0 $ – 0 $ – 0 $ – 0 $ – 0 $ – 0
TOTAL BENEFITS $ 134,434,000.00 $ 267,392,000.00 $ 398,958,000.00 $ 530,254,000.00 $ 662,120,000.00 $ 1,993,158,000.00
CLICK HERE TO CREATE SIMPLE COST BENEFIT ANALYSIS TEMPLATES IN SMARTSHEET

about:blank

Analysis Summary

SIMPLE COST BENEFIT ANALYSIS TEMPLATE
QUANTITATIVE ANALYSIS YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 TOTAL
BENEFITS
COST SAVINGS $ 134,225,000.00 $ 267,290,000.00 $ 398,580,000.00 $ 529,960,000.00 $ 661,630,000.00 $ 1,991,685,000.00
COST AVOIDANCE $ 154,000.00 $ 102,000.00 $ 298,000.00 $ 294,000.00 $ 490,000.00 $ 1,338,000.00
REVENUE $ 55,000.00 $ – 0 $ 80,000.00 $ – 0 $ – 0 $ 135,000.00
OTHER $ – 0 $ – 0 $ – 0 $ – 0 $ – 0 $ – 0
TOTAL BENEFITS $ 134,434,000.00 $ 267,392,000.00 $ 398,958,000.00 $ 530,254,000.00 $ 662,120,000.00 $ 1,993,158,000.00
ACCUMULATED BENEFITS $ 134,434,000.00 $ 401,826,000.00 $ 800,784,000.00 $ 1,331,038,000.00 $ 1,993,158,000.00
COSTS
NON-RECURRING $ 211,500.00 $ 267,000.00 $ 244,000.00 $ 229,200.00 $ 103,000.00 $ 1,054,700.00
RECURRING $ 887,327.00 $ 847,352.00 $ 887,327.00 $ 847,352.00 $ 887,327.00 $ 4,356,685.00
TOTAL COSTS $ 1,098,827.00 $ 1,114,352.00 $ 1,131,327.00 $ 1,076,552.00 $ 990,327.00 $ 5,411,385.00
ACCUMULATED COSTS $ 1,098,827.00 $ 2,213,179.00 $ 3,344,506.00 $ 4,421,058.00 $ 5,411,385.00
NET BENEFIT OR COST $ 133,335,173.00 $ 266,277,648.00 $ 397,826,673.00 $ 529,177,448.00 $ 661,129,673.00 $ 1,987,746,615.00

Cost Benefit Analysis

ACCUMULATED BENEFITS 134434000 401826000 800784000 1331038000 1993158000 ACCUMULATED COSTS 1098827 2213179 3344506 4421058 5411385

,

CMGT/545 v1

Project Plan Template

CMGT/545 v1

Page 2 of 5

University of Phoenix logo

Project Plan

.

Section 1: Summary

The purpose of this project is to migrate to the cloud. The scope includes transferring to the cloud within a 12-month period with a budget of $1,000,000. The project should include the license of software needed, security, without interrupting daily activities for long time. The software should be reliable and serve the customer needs. Business should operate smoothly. If software glitches occur, they should be able to be fixed in a short time. The user interface should be easy to navigate around. Also, we should consider of dependability, security, and the amount of time that the software will take to be available. Currently we are updating our servers from Windows Server 2012, to Windows Server 2019, so that should be taken into consideration.

Section 2: Phasing

Phase I: Scoping and Planning

Phase II: Order/Install Equipment

Phase III: Install/Test Software

Phase IV: Conduct Hardware/Software Testing

Phase V: Conduct Training

Phase VI: Implementation

and Roll out

Phase VII: Evaluation and Post Implementation

30 days 30 days 60 days 60 days 30 days 60 days 90 days

Section 3: Schedule – Milestones 

Deliverable

Recipients

Delivery Date

Delivery Method

Statement of Work

Subcontractors

1/1/2021

e-mail

Work Breakdown Structure

Integrators

1/1/2021

e-mail

Status Reports

C-level managers

2/1/2021

meetings

Hardware Installation

IT infrastructure Team

3/1/2021

On site

Software Installation

IT Installation team

5/1/2021

On site

Training

Employees

6/1/2021

In person

Implementation

c-level managers/It Group/Employees

8/1/2021

On site

Evaluation

c-level managers /IT Group

9/1/2021

On site

New customer login

Customers

12/5/2021

website

Section 4: Resources 

1. Development: During this phase, our company will be conducting a market research to identifying a viable option to migrating to a cloud-based system. An IT team will be assigned for this research. The results of the research will be compared and evaluated by the project management, in order to continue with the development of the project. Our team will need to be working with the third-party cloud company to implementing software and adjust the software based on our company’s needs.

2. Test: In this phase we will be investigating programming code and testing for various scenarios. A testing team shall be assigned to carrying out this phase. Temporary outages might occur during this phase.

3. Production: During this phase, our company will be deploying the new product in various locations. Our selected IT team might be travelling to other locations of our company to delivering the new product.

Section 5: Organization 

Project Team: This includes a group of resources that work on the deliverable of the full project.

Duties include:

· Completing the project tasks that are within the set budget, timeline, and meet required expectations

· Proactively communicate status and managing expectations

Project Manager/Leader: Manages the full project, which includes leading and planning the development of all aspects of the project.

Duties include:

· Developing a project plan

· Recruit staff

· Assign tasks and roles to project team members

· Provide current updates to upper management

Business Analysts: Responsible for guaranteeing that all requirements are met accurately and effectively before a solution is developed and implemented. Duties include:

· Gather requirements from business units

· Document all technical and business requirements

· Verify if project deliverables meet the requirements

· Test solutions

QA Manager: Help to convert project requirements and design documents into testing cases and scripts. These scripts are often used to verify if the system meets the needs of the client.

Database Administrator: Design and create the database and tables that will be used

Designer: Responsible for fully understanding the project requirements and build and design a solution to correlate to those needs.

· Determine the best approach to the solution

· Determine the model and scope of the solution

· Determine data needs

Tester: Tests the solution to ensure there are no defects before allowing finished product to be implemented into production

Section 6: Change Management 

The purpose of this change management plan is to ensure that an appropriate plan is in place regarding all facets of the project plan. This plan is designed to prepare the project stakeholders for any business and technical changes that result from the cloud migration project.

A change management team will be created to facilitate, communicate, analyze and implement changes. The Change Management team will consist of a Change Manager and a Change Analyst and the Project Manager.

The duties of each member are as follows:

The Change Manager:

· Be accountable for all changes resulting from the project

· Facilitate all communication between project management team and stakeholders

· Document all suggested changes and record said decisions on those changes

The Change Analyst:

· Identify, document, and assess changes for their impact on the project scope/cost/timeline

· Define and provide guidance on implementing changes

· Participate in change evaluation

· Monitor the effectiveness of made changes

The Project Manager:

· Work with change manager and change analyst to keep project scope updated with potential changes

· Communicate any potential changes with the project team

· Define new timelines and expectations as needed to project team and stakeholders

· Keep an open dialogue between the project team, change management team and the stakeholders.

Section 7: Risk Management  

Risks would include: delays such as in weather-related delays issues that would cause days of not working on the installation of the software, waiting on approvals for more resources, lack of communication between departments for approvals, hardware and software incompatibilities, or other pending issues, and difficulties in training on the new software. Also, website outages would affect customer logins. The risks should be identified and addressed immediately by the project manager in order to making adjustments as needed for the project.

Appendix

(The company will add any additional appendices as needed.)

Authors

Timothy Heaton

Dimitrios Kotrotsios

Jess Wert

Arneshia James

Kevin Moore

Copyright 2020 by University of Phoenix. All rights reserved.

Copyright 2020 by University of Phoenix. All rights reserved.

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteEdu. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

Do you need help with this question?

Get assignment help from WriteEdu.com Paper Writing Website and forget about your problems.

WriteEdu provides custom & cheap essay writing 100% original, plagiarism free essays, assignments & dissertations.

With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.

Chat with us today! We are always waiting to answer all your questions.

Click here to Place your Order Now