02 Jan Question 4. Question : (TCO 8) All projects
Question 1. Question : (TCO 4) An example of resource leveling would be
fast tracking a project to finish early.
crashing a project to meet a critical deadline.
ensuring resource usage is balanced.
removing work from a project to compress its schedule.
Question 2. Question : (TCO 6) You are the project manager of a major IT project in Italy. You review your earned value report and you see that your SPI is .68. What does this mean to you?
The project is doing fine. No corrective actions are needed.
The project is slightly ahead of schedule. No corrections are needed.
The project is slightly behind schedule. Corrections are needed.
The project is very much behind schedule. Immediate corrections are needed.
Question 3. Question : (TCO 4) Which of the below is an example of an indirect cost to a project?
Concrete needed to complete a parking garage
A consultant for an IT project
Boats for a river rescue
Janitorial services for an entire building
Question 4. Question : (TCO 7) Which of the following is an example of a formal verbal form of communication?
Meeting notes made at a meeting with the VP of the company
A presentation by the project team to senior management
Contracts with a client that have been reviewed by lawyers
A memo from the senior VP of the company
Question 5. Question : (TCO 8) What document provides the project manager with information concerning what department and what individual is to provide HR support to his or her project?
The WBS
The OBS
The RAM
The RBS
Question 6. Question : (TCO 8) You are the project manager of a large, virtual financial project. You want to improve the functioning of the project team. Which of the techniques below would not likely improve the effectiveness and efficiency of the project team?
Establish a code of conduct for the project team.
Create a process to handle conflict.
Ensure all members of the team fully understand the project scope.
Hold face-to-face meetings whenever possible.
Instructor Explanation: Chapter 6
Points Received: 0 of 5
Comments:
Question 7. Question : (TCO 9) Stand-up meetings in agile project management do all of the following except which?
Provide project status.
Report on anticipated issues.
Permit group problem resolution.
Enhance collaboration.
Question 8. Question : (TCO 6) To control your project, you decide to use milestone analysis. Which of the below is not a benefit of using milestone analysis to control a project?
Milestones eliminate unnecessary changes to a project.
Milestones align schedules with suppliers.
Milestones trigger other team members’ participation in the project.
Milestones allow for periodic review of the project.
Page: 1 2
(TCO 4) Compare and contrast top-down and three-point estimating techniques.
Question 2. Question : (TCO 6) You are comparing two projects. Using the data below, calculate the CV, SV, SPI, and CPI. Second, use the values to provide the status of each project. All values are in dollars.
Project A Project B
EV 450 550
PV 465 575
AC 425 650
Question 3. Question : (TCOs 4 and 6) Describe the 4-step general model of project control. Provide examples of each step.
Question 4. Question : (TCO 8) All projects suffer from some form of conflict at one time or another. List and describe four common sources of conflict on a project and provide examples of each from either a recent project or from your personal life.
Question 5. Question : (TCO 9) Agile project teams are typically co-located. Why is this so important to an agile project and what does it facilitate on an agile project?
Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteEdu. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.
Do you need help with this question?
Get assignment help from WriteEdu.com Paper Writing Website and forget about your problems.
WriteEdu provides custom & cheap essay writing 100% original, plagiarism free essays, assignments & dissertations.
With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.
Chat with us today! We are always waiting to answer all your questions.