02 Jan Purchases of raw materials
Question 1
0 / 6 pts
(TCO 9) MedicalTechnical, Inc. manufactures surgical instruments to the exacting specifications of various customers. During April 2005, Job 911 for the production of 4,500 instruments was completed at the following costs per unit.
Direct materials $ 60
Direct manufacturing labor 20
Allocated manufacturing overhead 80
$160
Final inspection of Job 911 disclosed 100 defective units and 50 spoiled units. The defective instruments were reworked at a total cost of $12,000, and the spoiled instruments were sold to a jobber for $3,000.
If the costs associated with spoilage and reworked units are considered as normal to manufacturing operations, the unit cost of the good units produced on Job 911 is
$165.
$164.
$162.
$160.
Question 2
6 / 6 pts
(TCO 9) Walbreck Company had the following production for the month of August.
Units
Work in process, August 1 6,000
Started during August 24,000
Completed and transferred to finished goods 18,000
Abnormal spoilage incurred 3,000
Work in process, August 31 9,000
Materials are added at the beginning of the process. As to conversion cost, work in process was 20% complete at the beginning and 70% complete at the end of the month. Spoilage is detected at the end of the process.
Using the weighted-average method, the equivalent units for August, with respect to conversion costs, were
30,000.
24,300.
23,700.
27,300.
Question 3
6 / 6 pts
(TCO 9) In manufacturing its products for the month of January 20XX, Sandusky Corporation incurred normal spoilage of $7,000 and abnormal spoilage of $3,000. How much spoilage cost should Sandusky charge as inventoriable for the month of January 20XX?
$0
$3,000
Correct!
$7,000
$10,000
Question 4
6 / 6 pts
(TCO 6) Libations Corporation manufactures a line of flags. The annual demand for its flag display is estimated to be 100,000 units. The annual cost of carrying one unit in inventory is $1.60, and the cost to initiate a production run is $50. There are no flag displays on hand, but Libations had scheduled 60 equal production runs of the display sets for the coming year, the first of which is to be run immediately. Libations Corporation has 250 business days per year. Assume that sales occur uniformly throughout the year and that production is instantaneous.
If Libations Corporation were to schedule 30 equal production runs of the flag display for the coming year, instead of 60 equal runs, the sum of carrying costs and set-up costs for the coming year would increase (decrease) by
$(166).
$-0-.
$166.
$1,500.
Question 5
0 / 6 pts
(TCO 6) Blaster began operations in June 20XX. Blaster manufactures vehicle seat covers using a just-in-time production system supported by a backflush costing system. This system has two trigger points: (1) the purchase of raw materials, and (2) the sale of finished good units. Standard unit costs are $40 for raw materials and $25 for conversion costs. Blaster writes off any underallocated or overallocated conversion costs immediately. The following data were available for June 20XX.
Production of good units 19,800
Sales of good units 19,750
Purchases of raw materials [20,000 units at $40] $800,000
Conversion costs incurred $496,000
The June ending total for all inventory balances is
$16,250.
$12,250.
$11,250.
$10,000.
Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteEdu. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.
Do you need help with this question?
Get assignment help from WriteEdu.com Paper Writing Website and forget about your problems.
WriteEdu provides custom & cheap essay writing 100% original, plagiarism free essays, assignments & dissertations.
With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.
Chat with us today! We are always waiting to answer all your questions.